Project Owner & Contact:

City of uvalde pool improvements phase i, ii

uvalde, tx

Contact:  joe jarosek

(830) 776-2624

 

Completion Date         Construction Volume
June 2014                     $108,466.00
Project Details:
This project included accessibility and facility improvements to the City of Uvalde Pool. The project developed as two separate contracts between 2013 and 2014 for budget reasons.
The work included accessible ramps, restrooms, and a lift. The aesthetic improvements included new sidewalks around the pool, new paint, and finished in the pool house. The colors were selected to enhance the relationship between the adjacent civic center and the pool house.
 
Project Team
Architect
Davis Powell Architecture Uvalde, TX
Project Manager/President
Ira West

 

  Dec 8, 2017   admin